PAVING SCHEDULE
Fiscal Year 2006 - 2007
The following streets are scheduled to be overlayed with 1-1/2" of hot-mix asphalt:
Completed
Barry Lane 10/20/06
Capen Street - Sage Park Rd. to Douglas St. 10/20/06
Cedar Road 9/22/06
Coach Circle 9/22/06
East Street
Hayes Drive 10/20/06
Hickory Drive 9/22/06
Highland Avenue 9/22/06
Hollowbrook Road 9/22/06
Lovell Avenue 9/22/06
Oxcart Drive 9/22/06
Pigeon Hill Road - Addison Rd. to Tire Country 10/20/06
Sage Park Road 9/22/06
Spruce Road 9/22/06
Surrey Lane
Tobey Avenue - Rt. 159 to Worthy St. 10/20/06
Valley View Drive (to be reclaimed) 10/20/06
West Rosemont Avenue 11/18/06
Winthrop Road 9/22/06
Work will involve minor detours and delays during daytime hours. Residents are requested not to park vehicles in the roadway so that the work could progress in a safe and timely manner.
If there are any questions, concerns or complaints, please feel free to call the Public Works Complex at 285-1855.
PAVING SCHEDULE
July, 2005 - June, 2006
The following streets are scheduled to be overlayed with 1-1/2" of hot-mix asphalt in FY06:
Completed
Douglas Street
Highland Avenue
Kennedy Road (Buckland to Palisado) July, 2005
Lovell Avenue
Millbrook Circle July, 2005
Mountain Road July, 2005
Portman Street July, 2005
Sheffield Drive July, 2005
Wilton Road July, 2005
Pavement reclamation with 1-1/2" of hot-mix asphalt overlay is planned for the following streets:
Hayes Drive (Rood Ave to Ford Rd)
Valley View Drive (Windsor Ave to #28)
A thin overlay of sections of the following streets will be done in FY06 as
preventive maintenance: Chestnut Drive
July, 2005 Indian Hill Road
July, 2005 Pigeon Hill Road
(Addison Rd to 186' E of Marshall Phelps Rd) Pigeon Hill Road (600'
E of Pigeon Hill to #400) July, 2005
Prospect Hill
Road (Poquonock Ave to West St) July, 2005 Sage Park Road
Work will involve minor detours and delays during daytime hours. Residents
are requested not to park vehicles in the roadway so that the work could progress
in a safe and timely manner. If there are any questions, concerns or complaints, please feel free to call
the Public Works Complex at 285-1855. PAVING SCHEDULE Fiscal Year 2004-2005 The following streets were overlayed with hot-mix asphalt
during October, 2004: Adam Hill Alcott Drive Brown Avenue Hilltop Road Hobson Avenue Midian Avenue Morris Drive Overlook Drive Peddler Drive Scarborough Road Summit Drive Sylvia Lane Village Lane A notice was sent to
residents living on these streets covering the details of this work. Work involved minor detours and delays during daytime hours. Residents
were requested not to park vehicles in the roadway so that the work could progress
in a safe and timely manner. Valley View Drive will also be improved in the 2004/2005 fiscal year;
however, the road will be reclaimed before being paved later in the year. If there are any questions, concerns or complaints, please feel free to call
the Public Works Complex at 285-1855.