Day Hill Road Pavement Reclamation and Resurfacing


Location: Day Hill Road

Day Hill Road Pavment Reclamation and Resurfacing

It is proposed to reclaim and resurface a portion of Day Hill Road, from Northfield Drive to near Addison Road, in both the eastbound and westbound directions. Day Hill Road was constructed in part during the 1970’s, and except for repairs and some minor overlays has continued to serve the commercial and industrial developments in the Day Hill Corporate Area. The pavement is showing signs of distress, and needs to be rehabilitated to support the ever increasing vehicular and heavy truck traffic. This project proposes to reclaim and overlay approximately 2700 linear feet of 4 lane roadway. New curbing and catch basin tops will be included.
Start Date : March 2008
Completion Date : August 2008
Cost : $1,200,000
Comments : This project will be partially funded by the Federal Surface Transportation Program, up to $700,000.