2017 Public Works Paving Program - Phase 1



2017 Public Works Paving Program - Phase 1
Expected project duration: June 19th, 2017 - October 31st, 2017

The following is a list of streets to be milled and repaved as part of the first phase of the 2017 Public Works Paving Program.  Work is scheduled to begin Monday, June 19, 2017.  This work will include minor delays; however, the road will remain open at all times.  During this time, please do not park vehicles in the roadway so that work may progress in a safe and timely manner.

 

Town Center Area 

  • Center Street
  • Mechanic Street
  • Union Street

 

Wilson Area

  • Aramamet Street
  • Attawanot Street
  • Lyme Street
  • Irving Street
  • Saville Street
  • Skitchewaug Street
  • Songonosk Street

 

Additional roadway milling and paving is planned for the 2017 calendar year under this program and a list of streets to be included in the next phase will be posted once funding is approved for fiscal year 2018.  If you have any questions regarding these projects you may contact Robert Jarvis, Town Engineer/Director of Public Works at (860) 285-1804.